Consumer Applications
FOX Sports Super Bowl 2025
FOX Sports contracted the design, deploy, and support over 15,000 square feet of mission-critical infrastructure for Super Bowl LIX in New Orleans. The project required modular, scalable, and rapidly deployable solutions to accommodate production, technical, and operational personnel supporting the largest televised event in the United States.
Infrastructure Delivered
- Over 15,000 square feet of secure, modular structures supporting broadcast production.
- [106x] 8×20’ Infinite Cubes and [8x] 8×8’ Mini Infinite Cubes forming a multi-story operations hub.
- 600+ solid insulated walls and glass panels for climate-controlled environments.
- Exterior open-air decks to accommodate staging and auxiliary needs.
- Dedicated technical spaces including server rooms, fiber hubs, and control centers.

Strategic Advantages & Logistics:
- Reduced trucking & transport footprint: [21x] 53’ trucks
- Minimal on-site labor required: [10x] skilled field technicians supported by [10x] local laborers.
Optimized Heavy Equipment Usage:
- 1 x 10-ton crane
- 2 x 12K telehandlers
- 2 x 5K forklifts

Deployment Timelines & Efficiency
- Executive Office Building (2,500 sq. ft.) – 5 days
- Operations Office Building (2,500 sq. ft.) – 5 days
- Two-Story Technical & Production Offices, Server Room (10,000 sq. ft.) – 10 days
- Individual office spaces & talent green rooms – 2-3 days/per
- Total teardown & strike – 14 days
Operational Challenges & Solutions
- HVAC: Over 800,000 BTUs deployed for climate control across multiple sites.
- Power Management: 1 megawatt of power allocated to technical infrastructure, ensuring redundancy for uninterrupted broadcasting.
- Scalability & Modularity: Structures reconfigured for multiple interior layouts based on evolving production needs.
- Strategic Site Deployment:
- FOX Sports TV Compound (Lot 4 – Adjacent to Superdome) ii. FOX Sports Fan Plaza (Exterior Fan Engagement Zone)
- Interior Stadium Locations (Satellite Broadcast & Talent Green Rooms)
Impact & Key Takeaways
- Over $8 million in high-end technical gear integrated into our structures.
- 3-month advanced planning & design phase to optimize efficiency and execution.